Client:

ISTHA

Project Type:

Transportation - Phase I Study , Phase II Design

Construction Cost:

$62,750,000

ISTHA I-355 Veterans Memorial Tollway

Spring Creek to 151st Street in Will County, IL

Project Description

HOH was responsible for Phase I Study and Phase II Design for paving and fine grading improvements for mainline and crossroad for the Veterans Memorial Tollway (I-355) from Spring Creek to 151st Street in Will County, IL. Contract I-05-7709. Construction Budget - $62,750,000.

Scope of Work 

  • This 6.5 mile project included mainline pavement of three lanes in each direction of the mainline I-355, full diamond

    interchange with IL Route 7 including ramps and signalized intersections, construction of cross road box culverts,

    detention basins and erosion control of cleared and graded areas.

  • The improvement included reconstruction of one half mile of IL Rte 7, to a six lane section leading to the new bridge

    over I-355 complete with two thru lanes in each direction and left and right turn lanes.

  • The new mainline pavement included a full length median barrier and full shoulders on the left and right including a

    gutter along the right edge of shoulder.

  • Traffic signals for the ramp intersections and the intersection with Gougar Road as well as full interchange lighting

    were provided.

  • The Phase I Study included a PDR, LDS, IDS’s, BCR’s, Barrier Warrant Analyses, and Traffic Management Analyses, and

    multiple Public Hearings.